A request for quotation is a small design document, not a price enquiry. The number that comes back tracks the information that went in: an RFQ that names an alloy, three independent tolerance callouts and an annual volume gets a manufacturable quote in one working day. One that says “similar to this sample” gets a budget range and a week of questions.
This checklist is the one our engineers use when they open a new enquiry. It is written for buyers and project engineers who need a comparable quote from more than one supplier — send the same twelve lines to each factory and the replies become easy to judge.
Start with the drawing, not the description
A dimensioned 2D PDF is the contractual reference; a STEP or IGES file is for geometry and CAM only. If a dimension on the PDF and the 3D model disagree, the PDF wins in production. Send both, and say which one governs. Native CAD files are useful for DFM but only make sense once an NDA and tooling-IP terms are in place; our NDA and tooling IP FAQ covers that ground.
The twelve-line checklist
| # | What to specify | Why the factory asks |
|---|---|---|
| 1 | Part name and what it does | A housing for a handheld device and a heat-sink enclosure are quoted very differently even at the same size. |
| 2 | 2D PDF plus 3D STEP/IGES | The PDF sets dimensions and tolerances; the 3D file lets us check tool pull-out and CNC access. |
| 3 | Alloy and temper | 6063-T5 is the default for extruded enclosures; 6061-T6 for structural machined parts. Our alloy selection guide explains the trade-off. |
| 4 | Envelope, wall thickness and section limits | A stable wall thickness of 0.3 mm is achievable; the circumscribing circle for an extrusion is 220 mm and stock length is 6 m. Long or thin sections drive the die design. |
| 5 | Tolerances, stated separately | Internal/external dimension ±0.04 mm, wall thickness ±0.02 mm and CNC end-face cut ±0.02 mm are three independent numbers. Saw cutting is ±0.2 mm; high-precision work reaches ±0.005 mm and grinding ±0.002 mm on request. See tolerance capability. |
| 6 | Prototype quantity and annual volume | MOQ is 500 / 1,000 / 5,000 pieces depending on process, with no fixed piece count beyond that. Volume decides whether a die pays for itself. |
| 7 | Surface finish and colour | Anodising, powder coating, 180# bead blasting and electrophoresis are all run in our own plant. Name the finish and send a physical chip for colour; a RAL code alone cannot define an anodised tone. See surface treatments. |
| 8 | Sealing or IP requirement | IP65–IP67 are standard targets, IP68 by agreement. Write the required depth and duration on the drawing — we test the finished unit by static immersion per GB/T 4208, not an air-tightness test. |
| 9 | Secondary operations | List CNC faces, holes, threads and assembly steps. Bending is a product-stage operation on an extruded part, not a standalone service. |
| 10 | Packaging and labelling | Protective film, partitioned cartons, barcodes and print position all affect unit price and should be fixed before tooling. |
| 11 | Documents you need | RoHS / REACH declarations, mill certificates and inspection reports are routine; our quality system is certified to ISO 9001:2015. Say which ones must ship with the first article. |
| 12 | Target price, date and Incoterm | A target tells us which process route to propose. A delivery port and Incoterm make the freight line comparable between suppliers. |
A template you can paste into an email
Project: Part name / function: Drawing revision (PDF) + 3D file: Alloy and temper: 6063-T5 / 6061-T6 / other Envelope (L x W x H) and wall thickness: Tolerances (dimension / wall / CNC face, separately): Finish + colour reference: IP rating and test depth / duration: Secondary operations (CNC, holes, threads, assembly): Quantity: prototype ___ / annual ___ Packaging and labels: Required documents: Target price, required date, port / Incoterm:
Three mistakes that add a week
“Make it like the sample”
A sample shows the shape, not the tolerance stack. Without a drawing there is nothing to inspect against, so the first articles become a negotiation. One dimensioned PDF removes that loop.
One blanket tolerance for every feature
Writing ±0.05 mm on everything, including a 6 m extrusion length, prices the part as if every surface were precision-ground. Separate the section, the wall and the machined faces; our DFM review guide shows where a looser callout costs nothing.
A prototype quantity with no volume
Tooling is quoted against expected life. Five pieces and five thousand a year lead to different die steel, different unit price and different MOQ. Give both numbers even if the annual figure is an estimate.
What the reply should contain
A useful quotation names the process route, the die cost, the unit price at your volume, the tolerance it holds, the finish and the inspection plan. Expect 7–10 days for a new die (15–20 for a complex hollow section), about 7 days for samples and 25–30 days for production; a die modification takes 3–5 days. Freight is usually 4–7 days depending on route. If a reply gives a single number without those lines, it is a guess rather than a quote.
Send the twelve lines with your drawing and we will return a DFM review and a quote with the process route written down. Start at request a quote, or read how we run extrusion and CNC machining in-house.
Have a project in mind? Send your drawing and get a DFM review plus tooling quote within one working day.