Get a QuoteUpload your drawing

Quality & PPAP

Have you submitted PPAP before, and which documents can you supply?

Yes — we have PPAP submission experience on enclosure programmes. Confirm the submission level (PPAP Level 1–5) and the element list your OEM expects, and we build the package around it: PSW, dimensional results, material certificates, control plan, PFMEA and capability data. One boundary stated up front: we hold ISO 9001 (GB/T 19001), not IATF 16949.

What we need you to confirm first

A PPAP package is defined by your OEM, not by us. Four questions decide what we can put together and how long it takes, and we ask all four in the first reply:

  1. Submission level — PPAP Level 1 to 5 (see the table below).
  2. Element list — which of the 18 standard PPAP elements your OEM actually wants. Most enclosure programmes ask for a subset, not all 18.
  3. CTQ features and target index — which dimensions are critical, and the Cpk/Ppk target (1.33 and 1.67 are the usual ones).
  4. Submission timing — at sample approval, before series release, or after a process change.

PPAP submission levels

LevelWhat is submittedSamplesReview location
1Part Submission Warrant only (plus appearance approval report where applicable)Retained at our plantCustomer side
2Warrant with limited supporting dataSamples submittedCustomer side
3Warrant with complete supporting dataSamples submittedCustomer side
4Warrant plus whatever else the customer definesAs defined by customerCustomer side
5Warrant with complete supporting dataSamples submittedReviewed on-site at our plant

Level 5 review happens at the plant that makes the parts — we host it in person or as a live video walk-through of the extrusion line, CNC section, anodising and QC room.

If all they want is a basic dimensional report: Level 1 or Level 2?

This is the most common case we see, and it is worth being precise, because “just send the dimensional report” usually is not Level 1. Level 1 submits the Part Submission Warrant only (plus the appearance approval report where applicable), and the supporting data, including the dimensional results, stays at our plant for you to request later. If your customer actually wants to receive the dimensional report with the submission, that is Level 2: warrant plus samples plus limited supporting data.

So the first question back to your customer is a single sentence: “Do you need the dimensional results submitted with the warrant (Level 2), or is the warrant on its own enough (Level 1)?” That answer decides whether we ship a document package or just a signed warrant.

What your customer asks forLevel that normally fitsWhat we sendEffect on timing
Signed warrant onlyLevel 1PSW (+ AAR where appearance is specified)None — ships with the first article
Warrant + dimensional report + material certificate, with samplesLevel 2PSW, full dimensional results (2D vision + CMM), mill certificate traceable to the billet heat, samplesNone — ships with the first article
The above plus process documents (flow, PFMEA, control plan)Level 3Level 2 set + process flow diagram, PFMEA, control planAdd document preparation time before submission
The above plus capability dataLevel 3, or Level 2 with Cpk/Ppk named by the customerAdds an initial process study on your CTQ featuresAdds a study run under production conditions

Two practical notes. First, Level 2 “limited supporting data” is defined by the customer, not by us — ask them which items they want and send us that list. Second, Level 1 and Level 2 normally ride along with the first-article shipment and cost you no schedule; Levels 3 and above are what add preparation time, and Cpk/Ppk is the item that adds the most.

Internal preparation checklist by level

Once your customer has answered, this is what we build on our side. The same first-article inspection produces the data for every level — the difference is what leaves the building.

Level 1 — warrant only

  • PSW prepared and signed under the contracting entity on your order.
  • Full dimensional report produced (2D vision for the cross-section, CMM for machined features) and held on file — sent only when your customer asks for it.
  • Material certificate traceable to the billet heat, held on file.
  • AAR where appearance is specified: reference limit sample signed and retained.
  • Press, bath and inspection records kept against the part number for traceability.

Level 2 — warrant + samples + limited supporting data

  • Everything above, and the dimensional report and material certificate ship with the submission instead of being held.
  • Sample parts taken from production tooling, not prototype tooling, at the count your customer specifies.
  • Anodising records where applicable — film thickness by eddy-current gauge on every load, sealing and abrasion data on request.
  • Packing and labelling to your customer’s specification.
  • Dependency: “limited supporting data” is defined by the customer, so we need their item list before we can finalise this set.

Level 3 — warrant + samples + complete supporting data

  • Everything in Level 2, plus the process documents: process flow diagram, PFMEA and control plan, built around the CTQ features your customer names.
  • Measurement system analysis — gauge R&R on the equipment used for CTQ checks, where required.
  • Initial process study — Cpk/Ppk to the sample plan and target index agreed before the run.
  • Checking-aid list and retained master sample, identified to the part number.
  • Third-party reports (SGS, TÜV, Intertek) where the customer wants an outside lab — arranged in advance, because the lab slot is booked before the parts are ready.

Timing: Levels 1 and 2 are prepared alongside tooling and first-article inspection, so they ship with the first article and add no schedule. Level 3 adds document preparation, and the capability study can only start once there is a production run — so it follows first-article approval rather than running in parallel with it.

What we need from your customer before we start

  1. Drawing in STEP / DWG with the revision level, and the CTQ feature list.
  2. The customer-specific requirements (CSR) document, if they have one.
  3. Sample quantity, ship-to address and packing specification.
  4. Target Cpk/Ppk and sample size, if capability data is in scope.
  5. Signed appearance limit sample where colour is critical.
  6. The legal entity they need on the warrant, if that is fixed by their purchasing system.

The 18 PPAP elements: what we supply, what comes from you

ElementSourceNote
1. Design recordsYour drawing + our DFM versionSend STEP/DWG; we return a marked-up DFM for sign-off
2. Engineering change documentsSharedRevision log kept from first article onwards
3. Customer engineering approvalYouRequired where your OEM mandates it
4. DFMEAYou (we feed manufacturing input)Design FMEA follows the design owner
5. Process flow diagramUsExtrusion → CNC → anodising → assembly → packing
6. PFMEAUsBuilt on our own process steps
7. Control planUsTied to the CTQ features you name
8. Measurement system analysisUsGauge R&R on the equipment used for CTQ checks, on request
9. Dimensional resultsUsFull layout: 2D vision for cross-sections, CMM for machined features, eddy-current gauge for film thickness
10. Material & performance test resultsUsMill certificate traceable to the billet heat; anodising film thickness, sealing quality and abrasion data
11. Initial process studiesUs, by agreementCpk/Ppk on named CTQ features — see below
12. Qualified laboratory documentationUs / third partySGS, TÜV or Intertek reports arranged on request
13. Appearance approval reportSharedAnodised colour needs a signed physical limit sample; see our ΔE guidance
14. Sample production partsUsFrom production tooling, not prototype tooling
15. Master sampleUsRetained and identified for the programme
16. Checking aidsUsList of fixtures and gauges used on the part
17. Customer-specific requirementsYouSend the CSR document with the enquiry
18. Part Submission Warrant (PSW)UsIssued under the contracting entity on your order

How we handle Cpk / Ppk

Capability data is a study, not a stock document, and this is where suppliers usually over-promise. Our position:

  • We run capability studies on the CTQ features you name, measured under production conditions on production tooling — Ppk for the initial study, Cpk once the process is statistically stable.
  • The target index and sample plan are agreed before the run, not after. Tell us the number (1.33 and 1.67 are the common ones) and the piece count at enquiry stage.
  • We do not send a generic capability study, because a study that does not describe your part is worse than no study — it fails your review and costs you the schedule.

Which entity signs the PSW

PPAP files usually get rejected on paperwork mismatches, so we state this before you ask. Documents are issued under the contracting entity named on your order — Shenzhen Fangda Aluminium Co., Ltd., USCC 91440300MA5F120U6U — while production is carried out at Xinkeyang Plastic & Hardware Factory, USCC 92440300L91061599E, in Guangming District, Shenzhen. Both codes are verifiable on gsxt.gov.cn. If your OEM requires one specific legal entity on the warrant, tell us at quotation stage and we align the paperwork then, not at submission.

What we will not claim

  • We do not hold IATF 16949. Where an OEM mandates IATF-certified supply, we say so in the first reply so you can decide early.
  • We do not claim UL, CE or FCC marks in our own name — those belong to the finished device.
  • We do not ship a pre-written capability study or a copied control plan.

Related: quality control and certifications, tolerance capability and factory audits and visits.

Still have a question? Send your drawing and we will answer within one working day.